| Summary |
| Meeting Type: Team of 9 |
| Date: Wednesday, April 7, 2010 |
Time: 9:30am – 11:30 am |
Location: Commerce 1 |
| Recorder: Ryan Curran |
| Attendees List |
| Debra, Susan, Sally, Sue, James, Ryan, Shantell, George, Salim |
| Agenda Items and Notes |
1. Discrepancy Table
- Discrepancy table in response to the initial prototype from Bean Creative was finalized and posted to basecamp.
2. Project Timeline
- Project Manager and Project Coordinator will meet on Monday to create a final timeline/calendar incorporating milestones from bean creative, usability test dates, and all final deliverables.
- Each sub-team(s) will create their own plan to be incorporated into the master schedule
3. Usability Candidates
- Project Coordinator will work with Rebecca to establish usability candidates for Round 2 of usability tests.
|
| Action Items |
| # |
Task |
Person responsible |
Due date |
| 1 |
Subteam(s) to submit individual timelines |
Team |
Sun. 11 Apr |
| 2 |
N/A |
|
|
| 3 |
N/A |
|
|
| 4 |
N/A |
|
|
| Next Meeting: Wednesday, April 14, 2010 9:30 am |